The Greenway's Future
(Updated
May 2008)
-
A government grant requesting funds
for Phase V (Raider Drive to Tinsley Park) was submitted in 2007. Phase
V will proceed north under Raider Drive, cross Mouse Creek behind Raider
Field and connect with the current Tinsley Park Trail. The plan is to
improve the Tinsley trail and connect with the Greenway at Mimosa Drive.
-
In the summer of 2008, a passage under
Paul Huff Parkway will connect with the completed section on the Home
Depot side of Paul Huff. The Greenway will proceed south to the City
school property.
-
Employees of the City of Cleveland
will complete a section of the Greenway from the City school property
south to an underpass of the new Mimosa Drive bridge.
-
A future phase calls for the southern
origination point of the greenway at the Village Green. This phase will
go under Inman Street (underpass already completed) and will terminate
at Willow Street.
-
In years to come, the greenway will
continue from Mohawk Drive to the Hiwassee River. The exact route and
surfaces have not been determined, but will likely incorporate the
Cleveland Utilities easement near the soccer complex.
-
“Spurs” of the original conception of
the Greenway (Village Green to Hiwassee) have been considered and
include a passage under 25th Street from Spring Creek development to Lee
University, a neighborhood connector north along Fillauer Branch, and
passage under Keith Street from Tinsley Park to the McKenzie Financial
Center.
(updated October 2006)
-
A government grant for
$496,987 was received in August of 2006 to fund Phase III from 20th
Street to Willow Street. It will include two paths under bridges: 20th
and 17th Streets. It will also include a footbridge between 17th Street
and Willow.
-
The Cleveland Rotary
Club dedicated a trailhead entrance at Willow as part of their Rotary
Centennial project in June 2006 and will be incorporated in Phase III.
-
In August of 1999
Bradley County was awarded a grant from the Recreation Trails Program to
acquire a 2-acre tract along Mouse Creek at Willow Street. This will
also be incorporated into Phase III.
-
A future phase calls for
the southern origination point of the greenway at the Village Green.
This phase will go under Inman Street (underpass already completed) and
will terminate at Willow Street.
-
Tentative plans for the
leg beginning at Raider Drive will proceed north under Raider Drive and
include natural, cement and asphalt surfaces following the current trail
to Tinsley Park.
-
In late 2006 and early
2007, the Tennessee Department of Transportation (TDOT) will be
replacing the bridge at Mimosa Drive and Mouse Creek Road and will be
installing an underpass for the Greenway as part of the project.
-
Cleveland Utilities is
currently constructing a water retainment and pumping station at Mimosa
between Mimosa Drive and Paul Huff Parkway along the proposed greenway
corridor. CU will work to prepare the path as budgets allow.
-
A $50,000 TDOT grant was
obtained in summer 2006 to partially fund the greenway to continue south
under Paul Huff parkway from the current Home Depot section.
-
In years to come, the
greenway will continue from Mohawk Drive to the Hiwassee River. The
exact route and surfaces have not been determined, but will likely
incorporate the Cleveland Utilities easement near the soccer complex.
|