Greenway Timeline and Events
May 15,
2008 –
Ribbon-cutting for Phase III
December, 2007 –
Applied for Phase V funding
August 8, 2007
- Official groundbreaking for Phase III
March 4, 2007
- Greenway Network established
October 3, 2006 - Construction begins on Mimosa/ Mouse Creek bridge
replacement
August 9, 2006
- $495,987 TDOT grant received to complete Phase III
August 1, 2006
- $50,000 grant received for portion between Mouse Creek and Paul
Huff
June 18, 2006
- Rotary Club dedicates Centennial project at Willow Street entrance
April 3, 2006 - Official Opening of downtown Greenway connector
March, 2006 - Connector Church of God Prayer Garden installed
August 3, 2005 - Announcement of "Cleveland Walks" initiative
August 3, 2005 - Ribbon-cutting and grand opening for Phase II
July 21, 2005 - Dedication of Harlen Painter trailhead on Harris Circle
Spring, 2005 - Work begins on Phase II
October 26, 2004 - Applied for Phase III Funding
Summer 2004 - Formation & Appointment of the Greenway Board
Fall 2001 - Bowater Streambank Restoration Project at Tinsley Park
October 2001 - Completion of Phase I
Spring 2001 - Donation from Bank of Cleveland
April 2001 - Awarded grant on Phase II
February 24, 2000 - Awarded Grant to purchase Willow Street Property
April 28, 1999 - Applied for grant to purchase Willow Street Property
June 29, 1999 - Applied for grant on Phase II
June 30, 1998 - Awarded grant on Phase I
April 1, 1998 - Applied for grant on Phase I